Finland's supervisory agency has ordered Google to stop clearing land at two planned data-centre sites, putting a permitting test in the path of a €13 billion AI buildout.

By THE COLDAI TIMES desk (AI-assisted)Editor: Dr. Shayan Salehi H.C.Published 5 min read1,033 words
Contextual file photo of Google's existing data centre at Hamina, Finland, seen across water; not one of the halted sites
Contextual file photo of Google's existing data centre at Hamina, Finland, seen across water; not one of the halted sites — IA · Googlen palvelinkeskus Hamina 1.jpg · Wikimedia Commons · CC BY-SA 4.0

Key facts

  • LVV ordered Tuike Finland to suspend preparatory work at Muhos and Kajaani no later than 23 October 2026, with a response due 14 October[1][3]
  • The halt covers tree felling, topsoil removal, digging and road building, while planning and surveys remain allowed[2]
  • Google said it fell short of its own high standards and will follow LVV's guidance; it says it acted under the Forestry Act[3][2][4]
  • Police opened a preliminary investigation at Muhos after a request filed on 2 October[4]
  • The sites belong to Google's €13 billion Finnish investment, tied to a 22-year deal for up to half of Loviisa nuclear output[1]

Finland's environmental regulator has told Google to stop clearing land at two planned data-centre sites until environmental impact assessments are finished. The order, reported on 7 October, halts groundwork on a hyperscale AI project already under way, and it lands on what Google calls its largest single investment in Europe.

What the regulator ordered

The Finnish Supervisory Agency, known as LVV, ordered Tuike Finland, the company acting for Google, to "immediately suspend, and no later than 23 October 2026" preparatory measures that would significantly alter the environment at the Muhos and Kajaani projects. Tuike must explain its plans by 14 October. If it does not comply, the agency can open enforcement proceedings.

According to The Next Web, the order covers tree felling, topsoil removal, digging, quarrying, crushing, moving soil, ditching, and building site roads and storage areas. Planning, measurements, soil surveys and other minor, easily reversible work remain allowed. The halt lasts until the environmental impact assessments for both projects are complete. The same report says the agency may use a conditional fine as an enforcement tool.

Tommi Muilu, head of LVV's environment department, said trees had been removed, topsoil stripped, site roads and storage areas built and ditches altered. In the agency's view, such measures "change the environment and cause impacts" that the assessment procedure exists to examine. The agency is investigating whether Tuike cleared hundreds of hectares of forest without the mandatory assessment. The Next Web reports that LVV first asked Tuike and both municipalities for explanations on 18 September, when public information indicated the Muhos site had lost about 300 hectares of forest.

None of the coverage cites a specific statute for the order, and the reports describe the legal basis only as the mandatory assessment requirement. The Next Web adds that local plans for both towns face appeals at an administrative court, so a building ban applies.

Google's response and the wider reaction

Google spokesman Sondre Ronander said in a statement, as quoted by Euronews, that the company understands the concerns and has "fallen short of our own high standards in this instance." He said Google would study LVV's findings and follow its guidance. The Next Web quotes the same statement as saying Google "acted in good faith under the Forestry Act" and ran nature surveys and protective measures for high-value areas. Google also says it is advancing landscaping and biodiversity plans, including tree planting across 130 hectares at Muhos.

Hanna Halmeenpaa, chair of the Finnish Association for Nature Conservation, told AFP that loggers had cut "nature sites which should be preserved" in a deforested area of more than 300 hectares. Environment and Climate Minister Sari Multala told Helsingin Sanomat that the projects will probably be delayed and that "this is a serious matter: all companies operating in Finland must comply with the law," according to Euronews.

A criminal strand has also opened. Yle News reports that, according to tabloid Iltalehti, police have started a preliminary investigation into the preparatory work at Muhos after a private individual filed a request on 2 October. Police are assessing whether there is enough evidence of a crime to open a formal pre-trial investigation. Yle says the reports do not indicate that any police inquiry covers Kajaani, and no crime has been established. Yle also notes that satellite images show changes at the Muhos site during 2026.

The investment behind the sites

In September, Google announced a €13 billion investment in Finnish digital infrastructure over two years to support its AI ambitions. Al Jazeera reports that projects are planned in Muhos, Vaala, Kajaani and Hamina, where Google already runs a data centre. The order names only Muhos and Kajaani.

The package is tied to power supply. Al Jazeera reports that Google's deal includes a 22-year agreement to buy up to half of the output of the Loviisa nuclear plant, which would extend the plant's expected operating life to 2050 from a previously planned 2030 shutdown. That makes the Finnish programme as much an energy story as a computing one, and it explains why the permitting dispute carries weight beyond two forest plots.

Why the order matters

The case illustrates a shift in where the bottleneck for AI capacity sits. For two years the constraint in most markets has been chips and grid connections. Finland's order points to a third gate: land-use and environmental law, applied to the groundwork that precedes any construction. The agency's position is that early clearing can itself fall under the assessment requirement.

For Google, the immediate cost is delay. Minister Multala's expectation of slippage is a political judgement, not a schedule from the company, and Google has not published a revised timeline in the sources reviewed. The reputational cost may be larger. Google acknowledged that it fell short of its own standards, yet also says it acted under the Forestry Act. The legal question of whether forestry rules or the assessment regime governed the work may still be argued.

The political context is also tightening. Al Jazeera reports that opposition parties last month called for a national permit system to prevent power shortages and rising energy prices. Centre Party leader Antti Kaikkonen told Reuters that Finland must ensure enough electricity and transmission capacity to power data centres, while the Social Democratic Party welcomes the investment but worries about its effect on power demand. The Next Web notes that from 2027 the EU will rate data centres on energy and water use.

What to watch

Three dates and questions frame the next few weeks. First, Tuike's written response is due on 14 October, and it will show whether Google contests the scope of the order or simply accepts it. Second, the stop-work deadline of 23 October sets the limit by which all covered activity must cease. Third, the police assessment at Muhos will determine whether the matter becomes a formal criminal investigation, which would raise the stakes for contractors as well as for Google.

Other operators planning large sites in forested areas will likely read the order as a lesson in sequencing: finish the assessment before clearing land. The outcome at Muhos and Kajaani will show how much friction environmental review adds to the build-out.